Illinois Administrative Code
Title 41 - FIRE PROTECTION
Part 175 - TECHNICAL REQUIREMENTS FOR UNDERGROUND STORAGE TANKS AND THE STORAGE, TRANSPORTATION, SALE AND USE OF PETROLEUM AND OTHER REGULATED SUBSTANCES
Subpart H - REMOVAL, ABANDONMENT AND CHANGE-IN-SERVICE
Section 175.830 - Removal of USTs
Universal Citation: 41 IL Admin Code ยง 175.830
Current through Register Vol. 48, No. 38, September 20, 2024
a) For tank and piping removals, the following requirements and procedures shall be followed:
1) Compliance with subsections (a)(2) through
(a)(18) is the responsibility of the licensed contractor.
2) Except as otherwise provided in this
Section, the procedures of API 1604, incorporated by reference in 41 Ill. Adm.
Code 174.210, shall be followed for
vapor freeing and inerting procedures.
3) Secure a removal permit and schedule
removal date with OSFM. When removed piping exceeds 20 feet or 50% of the total
piping run at a site, and for every tank removal, a removal permit is required
(in addition to any other permit that would normally be required). A new permit
and fee will be required when there is a failure to meet the Date Certain
schedule established under Section
175.320, including not showing
for the inspection, not being completely ready for the inspection, allowing the
permit to expire before the inspection, or not cancelling the job before 6:00
a.m. the morning of the scheduled activity. (See Section
175.300 for additional permit
requirements.)
4) Maintain all
combustible gas indicator equipment according to manufacturer's
specifications.
5) Establish an
exclusion zone within which smoking is prohibited, which shall include all
hazardous (classified) locations/areas where work related to removal is being
conducted. The use of spark producing/non-explosion proof equipment is
prohibited in the vapor hazard area prior to removal of product and sludges and
attaining the lower explosive limit (LEL)/oxygen levels required in subsection
(a)(9).
6) Excavate to the top of
the tank. Drain product from piping into the tank or into approved drums, being
careful to avoid any spillage to the excavation area. Safely disconnect product
piping from the tank. Further excavation below the top of the tank is not
allowed until STSS has verified that tank conditions meet the LEL/oxygen
criteria of subsection (a)(9).
7)
Remove all liquids from the tank using explosion-proof pumps or hand pumps.
When suctioning product out of tanks, plastic pipes shall not be allowed as a
suction tube.
8) Regularly monitor
the tank atmosphere and the excavation area with a combustible gas indicator
for flammable or combustible vapor concentration until the tank is removed from
both the excavation and the site. Monitoring the UST shall be done at 3 levels
in the tank: top, middle and bottom. A confined space entry permit shall be
obtained prior to tank entry and Safety Data Sheets (SDS) must be on
site.
9) Regularly monitor the tank
to ensure explosive conditions do not exist. A maximum of 5% of the LEL, or 5%
or less oxygen concentration, shall be attained before the tank is considered
safe for removal, instead of 10%, as required in the API 1604. Dry ice shall
not be allowed as a method of inerting tanks as referred to in API
1604.
10) Bond all devices to the
tank and ground the tank to a separate ground when vapor freeing the tank with
compressed air or using inert gases under pressure. When using inert gases the
cylinder shall be equipped with a pressure gauge, so that no more than 5 psi
can be discharged into the tank during vapor freeing procedures. To ensure and
maintain proper grounding and bonding, the connections shall be tested by the
contractor for continuity. This testing shall be done with equipment designed
for continuity testing. When vapor freeing of tanks, plastic pipes shall not be
allowed as a vent tube on eductors.
11) Plug and cap all accessible tank holes.
One plug should have an 1/8 inch vent hole.
12) Excavate around the tank to prepare for
removal. This shall include excavation along one side and one end, from top to
bottom.
13) A STSS shall be on site
before any tanks and piping are removed.
14) With STSS on site, remove tank and piping
from the ground. Equipment with sufficient lifting capacity shall be used to
lift the tank from the excavation and must be rated as appropriate for the
particular site and excavation.
15)
Protective Equipment and Tank Cleaning Requirements
A) Cleaning procedures shall be in accordance
with API 2015, incorporated by reference in 41 Ill. Adm. Code 174.210. Personal
protection requirements for tank cleaning personnel shall, at a minimum,
include the following:
i) protective
respiratory equipment for tank cleaning personnel shall be the type that
provides supplied positive air pressure to a full-face mask throughout the
breathing cycle during all cleaning operations, in accordance with API
2015;
ii) level B personal
protective equipment with body harness and tag line;
iii) protective booties;
iv) continual monitoring of LEL and oxygen
during cleaning; and
v)
attendant/observer.
B)
Requirements in subsection (a)(15)(A) shall not apply in the event that no
physical entry is made into the tank.
16) Any UST removed from the excavation zone
shall be properly cleaned on site the day of the removal and removed from the
site within 24 hours.
17) Tanks
larger than 2,000 gallons in capacity shall have holes or openings no less than
3 feet x 3 feet, one on each end or side, for cleaning. Tanks less than 2,000
gallons capacity shall have one entire side removed from end to end and shall
be no less than 3 feet wide.
18)
The use of spark producing/non-explosion proof equipment is prohibited in the
vapor hazard area prior to attaining the LEL/oxygen levels required in
subsection (a)(9).
19) If an STSS
observes evidence of a release, the owner, operator or designated
representative of the UST owner/operator must notify the Illinois Emergency
Management Agency-Office of Homeland Security (IEMA-OHS). This is to be done at
the site immediately following the field determination and the incident number
shall be given to the STSS prior to the STSS leaving the site.
20) All removals require a site assessment
pursuant to 41 Ill. Adm. Code
176.330.
21) Any tank being removed without an OSFM
permit will be required to be put back in the excavation and vented to 12 feet
above grade if it has not been removed from the site and covered with backfill
until a permit and licensed contractor can remove it properly.
b) Bunker Tanks
1) A commercial heating oil or emergency
power generator tank situated below grade, in a basement, on a floor, and
enclosed in a masonry wall structure, with the tank completely or partially
covered by sand, or otherwise not fully accessible to inspection, commonly
referred to as a "bunker tank", meets the definition of a UST (see 41 Ill. Adm.
Code 174.100). Removal of a bunker
tank shall require the owner or operator to hire a licensed decommissioning
contractor to secure proper permitting and schedule the removal pursuant to
Section 175.320.
2) That section of
the enclosing masonry partition wall that is not part of the building's
basement exterior wall will need to be dismantled, and all sand within the
enclosure removed. Both masonry rubble and sand from the enclosure will be
hauled off as special waste under manifest by a licensed waste hauler (see 35
Ill. Adm. Code 808 and 809).
3) The
exposed tank will be emptied as much as possible of any residual liquids, and
the area will be monitored for vapors, and ventilation provided as needed to
maintain LELs of 5% or less. No further work on the tank removal will be
allowed unless the STSS is on site.
4) With the STSS on site and LELs at a
maximum of 5%, the tank will be accessed for cleaning. Tanks larger than 2,000
gallons in capacity shall have holes or openings no less than 3 feet x 3 feet,
one on each end or side, for cleaning. Tanks less than 2,000 gallons capacity
shall have one entire side removed from end to end and shall be no less than 3
feet wide.
5) Once cleaned, the
tank will be cut up on site, the pieces removed from the building, and all
parts of the tank scrapped.
6) Once
the enclosure wall, sand and tank have been properly removed, the area where
the bunker tank had been will be evaluated under the direction of the STSS on
site.
A) For bunker tanks, soil sampling and
a site assessment will be required if either of the following conditions are
found:
i) Evidence indicating product may
have migrated from the bunker tank to the environment beyond the floor or walls
of the building it was located within, such as finding free product in a drain;
or
ii) Evidence is seen of both
leakage of product on the floor or building wall where the bunker tank was
located, and the area of floor or wall associated with evidence of leakage of
product from the bunker tank is deteriorated or cracked such that there is a
possibility of the product having migrated beyond the enclosure
confines.
B) In the
event that any of the conditions described in subsection (b)(6)(A)(i) or (ii)
are found, samples will be obtained from soil borings from beneath the floor or
from outside the wall from areas where contamination is most likely to be
present, based on the evidence discovered. Samples will be submitted for
analysis, and a release shall be reported if indicated.
C) In the event that none of the conditions
described in subsection (b)(6)(A)(i) or (ii) are found, no samples from soil
borings will be required, and no incident shall be reported.
D) The STSS on site will clearly document
STSS observations under "Remarks" on the Log of Removal, noting whether any of
the conditions listed in subsections (b)(6)(A)(i) and (ii) were
present.
7) In addition
to submitting the OSFM Site Assessment Results Report form, the following
supplemental documentation shall also be submitted to OSFM to properly close
the removal of a bunker tank. The form is available at the website cited in
subsection (a)(19). In the event there is "Contamination" being reported:
A) The report from the lab, including
analytical results derived from the soil samples showing locations of the
samples taken, shall be attached to the OSFM Site Assessment Results
Report;
B) The OSFM form indicating
"Contamination" shall be signed by a Professional Engineer or a Professional
Geologist;
C) The IEMA-OHS Incident
Number from the release report shall be recorded on the OSFM form;
and
D) The box indicating "Bunker
Tank" shall be marked on the OSFM form.
c) Disposal of Tanks
1) If a tank is to be scrapped as junk, it
shall be retested for combustible or flammable vapors and, if necessary,
rendered gas free.
2) If the tank
last contained leaded gasoline, an unknown petroleum product or a hazardous
substance, it may only be scrapped or junked, recertified, or discarded at a
special waste or hazardous waste landfill as designated by Illinois EPA
regulations. If tanks are being re-certified, the licensed contractor must give
written notice to OSFM on the removal permit as to the intent to re-certify and
re-use the tanks being removed. The re-certified tank must be re-installed
within 6 months from removal.
3)
Removed tanks may not be reused for any purpose other than those allowed by
OSFM rules (proper disposal at an approved landfill, scrapped or junked after
proper cleaning, or recertified pursuant to OSFM rules).
4) Compliance with this subsection (c) is the
responsibility of the licensed contractor.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.