Section 845.200 - Permit Requirements and Standards of Issuance
Universal Citation: 35 IL Admin Code ยง 845.200
Current through Register Vol. 48, No. 38, September 20, 2024
a) Permit Requirements
1) No person may construct, install, or
modify a CCR surface impoundment or related treatment or mitigation facilities,
including corrective action measures under Subpart F, without a construction
permit issued by the Agency under this Part.
2) Except as provided in Section
845.230(d),
no person may operate a CCR surface impoundment without an operating permit
issued by the Agency under this Part. For purposes of this Part, a CCR surface
impoundment starts operation upon initial receipt of CCR.
3) No person may perform corrective action at
a CCR surface impoundment without obtaining a construction permit for
corrective action and modifying the facility's operating permit, or modifying
the facility's operating permit when the approved corrective action does not
require the modification of the CCR surface impoundment or the installation or
modification of related treatment or mitigation facilities.
4) Except as provided in Section 22.59(e) of
the Act, no person may close a CCR surface impoundment without obtaining a
construction permit for closure issued by the Agency under this Part.
5) A CCR surface impoundment must maintain an
operating permit until:
A) The completion of
post-closure care when the CCR surface impoundment is closed with a final cover
system; or
B) The completion of
groundwater monitoring under Section 845.740(b) when the CCR surface
impoundment is closed by removal.
6) The Agency may issue a joint construction
and operating permit.
b) Standards for Issuance
1) Except as provided
in subsection (b)(2), the Agency may not issue any construction or operating
permit required by this Part unless the applicant submits adequate proof that
the CCR surface impoundment will be constructed, modified or operated so as not
to cause a violation of the Act or Board rules.
2) The existence of a violation of the Act,
Board regulation, or Agency regulation will not prevent the issuance of a
construction or operating permit under this Part if:
A) The applicant has been granted a variance
or an adjusted standard from the regulation by the Board;
B) The permit application is for
construction, installation, or operation of equipment to alleviate or correct a
violation; or
C) The permit
application is for construction, installation, or operation of equipment
necessary to restore, protect or enhance the environment.
3)
In granting permits, the Agency
may impose reasonable conditions specifically related to the applicant's past
compliance history with the Act as necessary to correct, detect, or prevent
noncompliance. The Agency may impose such other conditions as may be necessary
to accomplish the purpose of the Act and as are not inconsistent with this
Part. [415 ILCS
5/39(a)]
4)
In making its determinations on
permit applications under this Part, the Agency may consider
prior adjudications of noncompliance with the Act by the applicant that
involved a release of a contaminant into the environment.
[415 ILCS
5/39(a)]
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.