a) The cover of requirements of Section 807.305(a), (b) and (c) shall not apply to the on-site disposal of concrete waste resulting from the manufacturing operations of Cretex Pressure Pipe, Inc. (Cretex) at its South Beloit, Winnebago County, plant.
b) Disposal activities shall meet the following requirements:
1) Cretex
shall limit waste disposal to the types of waste disposed of pursuant to
variance granted in PCB 83-125, which are concrete waste, cull pipe, and metal
reinforcing rods embedded in concrete. Cretex shall take all reasonable
measures to minimize disposal of such metals as waste through use of recycling,
such as reuse of the metals on-site or sale or exchange of the metals through
the Illinois Industrial Materials Exchange Service.
2) Cretex shall limit the exposed, active
surface of its disposal site to a one acre area, and the height of the fill in
the active area to that of adjacent improved terrain.
3) Once a week, Cretex shall cover the
exposed, active surface of its disposal site with a compacted layer of at least
6 inches of earthen material.
4)
Within 60 days of cessation of disposal activities, in any one acre area,
Cretex shall provide any final, sloping faces of its disposal site with at
least two feet of final cover consisting of compacted earthen material. Cretex
shall insure that a vegetative cover is established to control
erosion.
5) Within 60 days of
cessation of disposal activities, Cretex shall provide any flat reclaimed area
of its disposal site which is to be used for the storage of pipe inventory and
equipment, or which is to be occupied by buildings, with at least six inches of
final cover consisting of silty sand or similar material. However, within 60
days of cessation of such uses, Cretex shall provide at least an additional 18
inches of final cover material as specified in subsection (b)(4)
above.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.