Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 807 - SOLID WASTE
Subpart F - FINANCIAL ASSURANCE FOR CLOSURE AND POST-CLOSURE CARE
Section 807.624 - Interim Formula for Cost Estimate
Current through Register Vol. 48, No. 38, September 20, 2024
a) An operator may temporarily utilize the formula of this Section for preparing a cost estimate instead of preparing a cost estimate based on closure and post-closure care plans. No permit application filed after March 1, 1985 may utilize this formula. Each operator must file an application to modify the site permit to include closure and post-closure care plans and cost estimates by March 1, 1988.
b) References to closure and post-closure care plans in financial assurance instruments shall be construed to refer to the closure and post-closure care requirements of this Part and the permit for the site.
c) This formula may not be utilized in lieu of the plans and cost estimates required under 35 Ill. Reg. Adm. Code 724 and 725.
d) The following abbreviations and symbols are used in the formula:
e) Area requiring final cover
A(2) |
= |
(Y)(A WR) |
= |
3 AWR |
3200 (AD) |
3200 AD |
f) Cost estimate (dollars)
CE = (CPA)(A) + 3((CPA)(P)(A) + 600(M))
= 5750A + 1800M