a) All reviews carried out under this Part shall be carried out by the Agency or a RELPE, both under the direction of aLicensed Professional Engineer. (Section 58.7(d) of the Act)
b) Plans, reports and related activities which the Agency or a RELPE may review include, but are not limited to:
c) Only the Agency shall have the authority to approve, disapprove, or approve with conditions a plan or report as a result of the review process, including those plans or reports reviewed by a RELPE. (Section 58.7(d)(3) of the Act)
d) Except as provided in subsection (d)(5) below and Section 740.705(c) of this Part, the Agency shall have 60 days from the receipt of any plan or report to conduct a review and make a final determination to approve or disapprove the plan or report, or approve the plan or report with conditions. All reviews shall be based on the standards set forth in this Subpart E.
e) Upon completion of the review, the Agency shall notify the RA in writing of its final determination on the plan or report. The Agency's notification shall be made in accordance with Section 740.215(b) of this Part. If the Agency disapproves a plan or report or approves a plan or report with conditions, the written notification shall contain the following information, as applicable:
f) The Agency may, to the extent consistent with review deadlines, provide the RA with a reasonable opportunity to correct deficiencies prior to sending a disapproval. However, the correction of such deficiencies by the submittal of additional information may, in the sole discretion of the Agency, restart the time for review.
g) If the RA has entered into a contract with a RELPE under Subpart B of this Part, the Agency shall assign plans and reports submitted by the RA to the RELPE for initial review.
h) If the Agency disapproves or approves with conditions a plan or report or fails to issue a final determination within the applicable review period and the RA has not agreed to a waiver of the deadline, the RA may, within 35 days after receipt of the final determination or expiration of the deadline, file an appeal with the Board. Appeals to the Board shall be in the manner provided for the review of permit decisions in Section 40 of the Act. (Section 58.7(d)(5) of the Act)