Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 740 - SITE REMEDIATION PROGRAM
Subpart D - SITE INVESTIGATIONS, DETERMINATION OF REMEDIATION OBJECTIVES, PREPARATION OF PLANS AND REPORTS
Section 740.410 - Form and Delivery of Plans and Reports, Signatories and Certifications
Current through Register Vol. 48, No. 38, September 20, 2024
a) All plans and reports prepared under this Part shall be submitted to the Agency on forms prescribed and provided by the Agency with attachments and accompanying documentation as necessary. Plans and reports shall be mailed or delivered to the address designated by the Agency on the forms. Plans and reports that are hand-delivered to the Agency shall be delivered during the Agency's normal business hours.
b) All plans and reports submitted to the Agency shall include:
"I attest that all site investigations or remedial activities, including review of laboratory data, that are the subject of this plan or report were performed under my direction and this document and all attachments were prepared under my direction or reviewed by me, and, to the best of my knowledge and belief, the work described in the plan or report has been designed or completed in accordance with the Act, 35 Ill. Adm. Code 740, and generally accepted engineering practices, and the information presented, including any qualified laboratory data, is accurate and complete."
c) If the investigation relies in whole or in part upon investigations or remedial activities conducted before the affirming LPE's assumption of responsibility for site activities, then the LPE is not required to affirm that those portions of the investigation or remedial activities were carried out under his or her direction. However, the LPE shall review the documentation of the prior investigations or remedial activities and evaluate their suitability for compliance with Title XVII of the Act and this Part. Such information may be submitted to the Agency for consideration along with the LPE's written evaluation of suitability, but the Agency shall not be required to accept the information as evidence of compliance with any requirements of the Act or this Part.
d) The RA may elect to prepare and submit for review and approval any and all reports and plans required under this Part individually following the completion of each such activity or concurrently following the completion of all activities, or in any other combination. [415 ILCS 5/58.6(f)]