Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 734 - PETROLEUM UNDERGROUND STORAGE TANKS
Subpart H - MAXIMUM PAYMENT AMOUNTS
Section 734.825 - Soil Removal and Disposal
Current through Register Vol. 48, No. 38, September 20, 2024
Payment for costs associated with soil removal, transportation, and disposal must not exceed the amounts set forth in this Section. Such costs must include, but are not limited to, those associated with the removal, transportation, and disposal of contaminated soil exceeding the applicable remediation objectives or visibly contaminated fill removed pursuant to Section 734.210(f) of this Part, and the purchase, transportation, and placement of material used to backfill the resulting excavation.
a) Payment for costs associated with the removal, transportation, and disposal of contaminated soil exceeding the applicable remediation objectives, visibly contaminated fill removed pursuant to Section 734.210(f) of this Part, and concrete, asphalt, or paving overlying such contaminated soil or fill must not exceed a total of $57 per cubic yard.
(Excavation Length x Excavation Width x Excavation Depth) x 1.05
A conversion factor of 1.5 tons per cubic yard must be used to convert tons to cubic yards.
b) Payment for costs associated with the purchase, transportation, and placement of material used to backfill the excavation resulting from the removal and disposal of soil must not exceed a total of $20 per cubic yard.
(Excavation Length x Excavation Width x Excavation Depth) x 1.05
A conversion factor of 1.5 tons per cubic yard must be used to convert tons to cubic yards.
c) Payment for costs associated with the removal and subsequent return of soil that does not exceed the applicable remediation objectives but whose removal is required in order to conduct corrective action must not exceed a total of $6.50 per cubic yard. The volume of soil removed and returned must be determined by the following equation using the dimensions of the excavation resulting from the removal of the soil:
(Excavation Length x Excavation Width x Excavation Depth)
A conversion factor of 1.5 tons per cubic yard must be used to convert tons to cubic yards.