Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 705 - PROCEDURES FOR PERMIT ISSUANCE
Subpart B - PERMIT APPLICATIONS
Section 705.126 - Decision Schedule

Current through Register Vol. 48, No. 38, September 20, 2024

For each permit application from a major new HWM facility or major new UIC injection well, the Agency must, no later than the effective date of the application, prepare and mail to the applicant a projected decision schedule. The schedule must specify target dates by which the Agency intends to do the following:

a) Prepare a draft permit pursuant to Subpart C;

b) Give public notice pursuant to Subpart D;

c) Complete the public comment period, including any public hearing pursuant to Subpart E; and

d) Issue a final permit pursuant to Subpart F.

BOARD NOTE: Derived from 40 CFR 124.3(g) (2017).

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.