Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 704 - UIC PERMIT PROGRAM
Subpart G - FINANCIAL RESPONSIBILITY FOR CLASS I HAZARDOUS WASTE INJECTION WELLS
Section 704.212 - Cost Estimate for Plugging and Abandonment
Current through Register Vol. 48, No. 38, September 20, 2024
a) The owner or operator must prepare a written estimate, in current dollars, of the cost of plugging the injection well in accordance with the plugging and abandonment plan, as specified in Sections 704.150 and 704.181(f). The cost estimate must equal the cost of plugging and abandonment at the point in the facility's operating life when the extent and manner of its operation would making plugging and abandonment the most expensive, as indicated by its plan.
b) The owner or operator must adjust the cost estimate for inflation within 30 days after each anniversary of the date on which the first cost estimate was prepared. The adjustment must be made as specified in subsections (b)(1) and (b)(2), using an inflation factor derived from the annual update to "Oil and Gas Lease Equipment and Operating Costs 1987 to [Date]" published by the U.S. Department of Treasury. The inflation factor is the result of dividing the latest published annual Index by the Index for the previous years.
BOARD NOTE: Corresponding
40 CFR
144.62(b) cites "Oil and Gas
Field Equipment Cost Index" without attribution of its source. The Board has
located a publication entitled "Oil and Gas Lease Equipment and Operating Costs
1987 to [Date]". It is assembled by the U.S. Department of Energy, Energy
Information Administration. It is available only on the Internet at
c) The owner or operator must review the cost estimate whenever a change in the plan increases the cost of plugging and abandonment. The revised cost estimate must be adjusted for inflation as specified in subsection (b).
d) The owner or operator must keep the following at the facility during the operating life of the facility: the latest cost estimate prepared in accordance with subsections (a) and (c) and, when this estimate has been adjusted in accordance with subsection (b), the latest adjusted cost estimate.
BOARD NOTE: Derived from 40 CFR 144.62 (2017).