Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 703 - RCRA PERMIT PROGRAM
Subpart G - CHANGES TO PERMITS
Section 703.271 - Causes for Modification
Current through Register Vol. 48, No. 38, September 20, 2024
The following are cause for modification, but not reissuance, of permits; the following are cause for reissuance as well as modification when the permittee requests or agrees:
a) Alterations. There are material and substantial alterations or additions to the permitted facility or activity that occurred after permit issuance which justify the application of permit conditions that are different or absent in the existing permit.
b) Information. The Agency has received information. Permits will be modified during their terms for this cause only if the information was not available at the time of permit issuance (other than revised regulations, guidance, or test methods) and would have justified the application of different permit conditions at the time of issuance.
c) New statutory requirements or regulations. The standards or regulations on which the permit was based have been changed by statute, through promulgation of new or amended standards or regulations, or by judicial decision after the permit was issued.
d) Compliance schedules. The Agency determines good cause exists for modification of a compliance schedule, such as an act of God, strike, flood, materials shortage, or other events over which the permittee has little or no control and for which there is no reasonably available remedy.
e) The Agency must also modify a permit as follows:
f) Notwithstanding any other provision of this Section, when a permit for a land disposal facility is reviewed under 35 Ill. Adm. Code 702.161(d), the Agency must modify the permit as necessary to assure that the facility continues to comply with the currently applicable requirements in this Part and 35 Ill. Adm. Code 702, 703, and 720 through 727.
BOARD NOTE: Derived from 40 CFR 270.41(a) (2005).