Section 602.320 - Partial Operating Permits

Current through Register Vol. 48, No. 38, September 20, 2024

a) If all phases of a construction project will not be completed at one time, the Agency must issue a partial operating permit under Section 602.105 upon receipt of:

1) a cover letter describing which sections of the project are completed;

2) a general layout plan sheet of the project indicating the location of water mains, treatment processes, or storage facilities to be operated;

3) a completed and signed operating permit application; and

4) bacteriological analysis results from water samples collected from the completed section of the project verifying satisfactory disinfection in accordance with Section 602.310.

b) Additional operating permits may be obtained in accordance with this Section as other portions of the project are completed.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.