Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 602 - PERMITS
Subpart B - CONSTRUCTION PERMITS
Section 602.205 - Preliminary Plans
Universal Citation: 35 IL Admin Code ยง 602.205
Current through Register Vol. 48, No. 38, September 20, 2024
a) To expedite the review of subsequent construction permit application plan documents, preliminary plans may be submitted prior to the submission of a construction permit application. No construction permit may be issued until the completed application, required fee, plans, and specifications have been submitted.
b) If preliminary plans are submitted, as directed under the Illinois Drinking Water Revolving Loan Funding Process (see 35 Ill. Adm. Code 664), the documents must include a description of alternate solutions, a discussion of the alternatives, and reasons for selecting the alternative recommended.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.