Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 375 - COMBINED SEWER OVERFLOW EXCEPTION CRITERIA AND FIRST FLUSH DETERMINATION
Subpart B - WATER QUALITY INVESTIGATION
Section 375.206 - Time Schedule

Current through Register Vol. 48, No. 12, March 22, 2024

a) Once a water quality investigation is initiated, every effort shall be made to expedite each step of the activity, completing the investigation in the shortest possible time without compromising the validity of the findings. Effective field activities are dependent upon proper seasonal, hydrologic and meteorologic conditions which will require flexibility in scheduling. Nevertheless the following time table is suggested as a general guideline.

b) Phase I - 30 to 60 days for completion plus 30 to 60 days for Agency review and planning of Phase II.

c) Phase II - 30 to 60 days for completion plus 30 to 60 days for Agency review and planning of Phase III.

d) Phase III - 6 months to 1 year and generally containing the summer months of June, July and August.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.