Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 371 - REQUIREMENTS FOR PLANS OF OPERATION AND OPERATION AND MAINTENANCE MANUALS
Subpart D - ELEMENTS OF PLANS OF OPERATION
Section 371.164 - Process Control and Start-up Procedures
This element of the PO must identify actions and related implementation schedules necessary for facility start-up and process control. Personnel responsible for the completion of each action must be identified by name and title. Reference must be made to the chapters of the O&M Manual where the facility start-up and process control procedures are discussed.
ACTION |
START DATE |
END DATE |
RESPONSIBLE PERSONNEL |
|
a) |
Prepare and submit a Start-up Services proposal to obtain funding for grant eligible portions of the training program. |
|||
b) |
Provide the beginning and completion dates for the Start-up Services and state the total time (person-days) to be spent on the services. |
|||
c) |
Outline a schedule for "wet" and "dry" testing and calibration of equipment. Identify specific units, processes, and equipment to be tested and calibrated. |
|||
d) |
Begin the sampling program to define the facility influent characteristics. |
|||
e) |
Identify all unusual waste discharges. |
|||
f) |
Develop an action plan for process control and "fine tuning." |
|||
g) |
Review process control and detailed start-up procedures with laboratory and operating staff. |
|||
h) |
Finalize the system and procedures for notification of unusual industrial waste discharges. |
|||
i) |
Test to determine capacity, motor running amps, temperature and vibration. |
ACTION |
START DATE |
END DATE |
RESPONSIBLE PERSONNEL |
j) |
Conduct equipment start-up and process control drills. |