Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 367 - PROCEDURES FOR ISSUING FINANCIAL ASSISTANCE AWARDS UNDER THE ILLINOIS CLEAN LAKES PROGRAM
Subpart G - ASSISTANCE AWARD CONDITIONS AND LIMITATIONS
Section 367.790 - Final Inspection for Phase II and LQMP Projects

Current through Register Vol. 48, No. 12, March 22, 2024

The award recipient shall notify the Agency in writing within 30 days after the completion of Phase II implementation project activities. The Agency will schedule a final inspection of the project within 60 days after the receipt of the notice.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.