Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 367 - PROCEDURES FOR ISSUING FINANCIAL ASSISTANCE AWARDS UNDER THE ILLINOIS CLEAN LAKES PROGRAM
Subpart G - ASSISTANCE AWARD CONDITIONS AND LIMITATIONS
Section 367.730 - Agreement Period
Current through Register Vol. 48, No. 38, September 20, 2024
a) Phase I Studies
Financial assistance agreements for Phase I studies shall have a maximum term of 36 months. The lake owner may, however, apply to the Agency in writing for a no-cost time extension of up to six additional months.
b) Phase II Implementation
Financial assistance agreements for Phase II implementation projects shall have a maximum term of 60 months. The lake owner may, however, apply to the Agency in writing for a no-cost time extension of up to 12 additional months.
c) LQMP Implementation
Financial assistance agreements for LQMP implementation shall have a maximum term of 18 months. A lake owner may apply to the Agency in writing for a no-cost time extension of up to six additional months in cases where seasonal or other physical lake conditions prevent completion of the project within an 18-month period.