Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 367 - PROCEDURES FOR ISSUING FINANCIAL ASSISTANCE AWARDS UNDER THE ILLINOIS CLEAN LAKES PROGRAM
Subpart D - ASSISTANCE APPLICATIONS
Section 367.410 - Assistance Award Pre-Application

Current through Register Vol. 48, No. 38, September 20, 2024

Lake owners seeking Phase I, Phase II or LQMP funding assistance shall submit the following pre-application information to the Agency by August 31 of each year:

a) Lake name;

b) Lake location (city and county);

c) Name of local project sponsor (grant applicant, source of local match);

d) Name, address and telephone number of local contact;

e) Name, address and telephone number of person who prepared application;

f) Type of award requested (Phase I, Phase II or LQMP);

g) Estimated project cost;

h) Estimated local match for project;

i) Project period;

j) Lake characteristics:

1) Surface area (acres and hectares);

2) Mean depth (feet and meters);

3) Maximum depth (feet and meters);

4) Volume (acre-feet and cubic meters);

5) Retention time (in years, if available);

6) Type of lake and year constructed (if applicable);

k) Watershed characteristics (in acres and hectares and percentage of total area):

1) Total watershed area;

2) Cropland;

3) Pasture;

4) Forest;

5) Urban;

6) Other;

l) Lake ownership and access:

1) Specific description of lake bottom ownership;

2) Specific description of the degree of public access to lake shoreline;

m) Lake use:

1) List of major uses associated with the lake;

2) List of available recreational facilities;

3) Estimated annual recreational use in visitor days (1 user per day = 1 visitor day);

4) Public water supply usage (population served and millions of gallons per day);

n) A brief description of the lake's history, use, importance and watershed conditions;

o) A brief description of the lake's impaired uses and water quality problems, including the causes of the problems;

p) A brief description of the lake restoration plan including, for Phase I projects, the measures anticipated; and, for Phase II or LQMP projects, the measures planned to be implemented and the estimated cost of each measure;

q) A brief description of the level to which the watershed area has been protected to prevent pollution of the lake;

r) A brief description of the history of any lake restoration or any previous local efforts to solve the existing problems.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.