Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 365 - PROCEDURES FOR ISSUING LOANS FROM THE WATER POLLUTION CONTROL LOAN PROGRAM
Subpart A - INTRODUCTION
Section 365.160 - Application Process

Current through Register Vol. 48, No. 38, September 20, 2024

a) In order to receive a loan under the WPCLP, loan applicants must apply to the Agency using the loan application process outlined in Subpart C. The process requires that:

1) the loan applicant submits a Funding Nomination Form pursuant to Section 365.310;

2) the loan applicant submits a Project Plan pursuant to Section 365.320;

3) the project undergoes State environmental review under Section 365.330;

4) the project be placed on the Project Priority List pursuant to Section 365.340; and

5) the loan applicant submits the following information:
A) a loan application as required by Section 365.350(a);

B) contracts for personal or professional services as required by Section 365.350(b);

C) a construction permit application, if necessary, as required by Section 365.350(c);

D) pre-bidding plans and specifications with certification form, as required by Section 365.350(d); and

E) bidding evaluation and certification forms as required by Section 365.350(e).

b) Loan applicants shall not execute a notice to proceed authorizing the initiation of construction until the loan agreement has been fully secured and executed.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.