Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 325 - PERMIT FEES FOR NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM PERMITS AND DOMESTIC SEWAGE SLUDGE GENERATOR OR SLUDGE USER PERMITS
Subpart B - PROCEDURES FOR DETERMINATION AND PAYMENT OF FEES FOR NPDES PERMITS AND SLUDGE GENERATOR OR SLUDGE USER PERMITS
Section 325.210 - Proration of Fees
Universal Citation: 35 IL Admin Code ยง 325.210
Current through Register Vol. 48, No. 38, September 20, 2024
a) Proration of New Permit Fees
1) In the case of a new NPDES
or sludge permit issued during the months of January through June, the Agency
may prorate the initial annual fee payable under this Section. [415 ILCS
5/12.5(c)] There is no proration of
construction site stormwater discharge NPDES permit fees.
2) Applicants for new NPDES or sludge permits
issued between July 1 and December 31 must pay the entire fee due under Section
325.205.
3) Applicants for new NPDES or sludge permits
issued between January 1 and May 31 will be charged a prorated fee according to
the following schedule based on the month in which the permit is issued.
A) January: 50 percent of the appropriate
annual fee amount or $250, whichever is greater.
B) February: 40 percent of the appropriate
annual fee amount or $250, whichever is greater.
C) March: 30 percent of the appropriate
annual fee amount or $250, whichever is greater.
D) April: 20 percent of the appropriate
annual fee amount or $250, whichever is greater.
E) May: 10 percent of the appropriate annual
fee amount or $250, whichever is greater.
4) For new NPDES or sludge permits issued in
June, the applicant must pay the entire annual fee for the following fiscal
year prior to issuance of the permit.
5) The minimum fee that may be paid pursuant
to this subsection (a) is $250.
b) Proration of Fees Due Following Permit Modifications.
If a requested modification to an existing NPDES permit causes a change in the applicable fee categories under Section 325.205 that results in an increase in the required fee, the permittee must pay to the Agency the amount of the increase, prorated for the number of months remaining prior to the next July 1, before the modification is granted. [415 ILCS 5/12.5(c)] For purposes of calculating the prorated fee due under this subsection, partial months will be rounded down to the nearest whole month.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.