a) The Agency may request additional information as needed to make a completeness determination. The Agency may to the extent practicable provide the applicant with a reasonable opportunity to correct deficiencies prior to a final determination of completeness. (See Section 39.5(5)(f) of the Act)

b) If, while processing an application that has been determined or deemed to be complete, the Agency determines that additional information is necessary to evaluate or take final action on that application, it may request such information in writing and set a reasonable deadline for response.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.