Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 270 - CLEAN AIR ACT PERMIT PROGRAM PROCEDURES
Subpart C - CAAPP APPLICATIONS
Section 270.304 - Effect of a Timely and Complete Application Submittal
Universal Citation: 35 IL Admin Code ยง 270.304
Current through Register Vol. 48, No. 38, September 20, 2024
a) An owner or operator of a CAAPP source shall not be in violation of the requirement to have a CAAPP permit under Section 39.5 of the Act if such owner or operator has submitted a timely and complete CAAPP application, until the Agency takes final action on the CAAPP application except as provided in subsection (b) below.
b) If the owner or operator of a CAAPP source fails to submit additional information requested by the Agency by the reasonable deadline specified pursuant to Section 270.305 of this Part, the owner or operator shall lose the protection provided in subsection (a) above.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.