Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 225 - CONTROL OF EMISSIONS FROM LARGE COMBUSTION SOURCES
Subpart E - CAIR NO[x] OZONE SEASON TRADING PROGRAM
Section 225.535 - Methodology for Calculating Ozone Season Allocations
Current through Register Vol. 48, No. 38, September 20, 2024
The Agency will calculate converted gross electrical output (CGO), in MWh, for each CAIR NOx Ozone Season unit that has operated during at least one control period prior to the calendar year in which the Agency reports the allocations to USEPA as follows:
a) For control periods 2009, 2010, and 2011, the owner or operator of the unit must submit in writing to the Agency, by September 15, 2007, a statement that either gross electrical output data or heat input data is to be used to calculate converted gross electrical output. The data shall be used to calculate converted gross electrical output pursuant to either subsection (a)(1) or (a)(2) of this Section:
CGO (in MWh) = GO (in MWh) a 1.0;
CGO (in MWh) = GO (in MWh) a 0.6; or
CGO (in MWh) = GO (in MWh) a 0.4.
CGO (in MWh) = HI (in mmBtu) a 0.0967;
CGO (in MWh) = HI (in mmBtu) a 0.0580; or
CGO (in MWh) = HI (in mmBtu) a 0.0387.
b) For control periods 2012 and 2013, the owner or operator of the unit must submit in writing to the Agency, by June 1, 2008, a statement that either gross electrical output data or heat input data is to be used to calculate the unit's converted gross electrical output. The unit's converted gross electrical output shall be calculated pursuant to either subsection (b)(1) or (b)(2) of this Section:
CGO (in MWh) = GO (in MWh) a 1.0;
CGO (in MWh) = GO (in MWh) a 0.6;
CGO (in MWh) = GO (in MWh) a 0.4.
CGO (in MWh) = HI (in mmBtu) a 0.0967;
CGO (in MWh) = HI (in mmBtu) a 0.0580; or
CGO (in MWh) = HI (in mmBtu) a 0.0387.
c) For control period 2014 and thereafter, the unit's gross electrical output will be the average of the unit's two most recent control period's gross electrical output, if available. If a unit commences commercial operation in the most recent control period and does not have gross electrical output from the most recent control period, e.g., if the unit commences commercial operation in the 2009 control period and does not have gross electrical output from the 2008 control period, gross electrical output from the 2009 control period will be used. If a generator is served by two or more units, the gross electrical output of the generator will be attributed to each unit in proportion to the unit's share of the total control period heat input of these units for the control period. The unit's converted gross electrical output will be calculated as follows:
CGO (in MWh) = GO (in MWh) a 1.0;
CGO (in MWh) = GO (in MWh) a 0.6; or
CGO (in MWh) = GO (in MWh) a 0.4.
d) For a unit that is a combustion turbine or boiler and has equipment used to produce electricity and useful thermal energy for industrial, commercial, heating, or cooling purposes through the sequential use of energy, the Agency will add the converted gross electrical output calculated for electricity pursuant to subsection (a), (b), or (c) of this Section to the converted useful thermal energy (CUTE) to determine the total converted gross electrical output for the unit (TCGO). The Agency will determine the converted useful thermal energy by using the average of the unit's control period useful thermal energy for the prior two control periods, if available. In the first control period for which the unit is considered to be an existing unit rather than a new unit, the unit's control period useful thermal output for the prior year will be used. The converted useful thermal energy will be determined using the following equations:
CUTE (in MWh) = UTE (in mmBtu) a 0.2930;
CUTE (in MWh) = UTE (in mmBtu) a 0.1758; or
CUTE (in MWh) = UTE (in mmBtu) a 0.1172.
e) The CAIR NOx Ozone Season unit's converted gross electrical output and converted useful thermal energy in subsections (a)(1), (b)(1), (c), and (d) of this Section for each control period will be based on the best available data reported or available to the Agency for the CAIR NOx Ozone Season unit pursuant to the provisions of Section 225.550.
f) The CAIR NOx Ozone Season unit's heat input in subsections (a)(2) and (b)(2) of this Section for each control period will be determined in accordance with 40 CFR 75, as incorporated by reference in Section 225.140.