Section 225.220 - Clean Air Act Permit Program (CAAPP) Permit Requirements
Universal Citation: 35 IL Admin Code ยง 225.220
Current through Register Vol. 48, No. 38, September 20, 2024
a) Application Requirements.
1) Each source with one or more EGUs subject
to the requirements of this Subpart B is required to submit a CAAPP permit
application that addresses all applicable requirements of this Subpart B,
applicable to each EGU at the source.
2) For any EGU that commenced commercial
operation:
A) on or before December 31, 2008,
the owner or operator of such EGUs must submit an initial permit application or
application for CAAPP permit modification that meets the requirements of this
Section on or before December 31, 2008.
B) after December 31, 2008, the owner or
operator of any such EGU must submit an initial CAAPP permit application or
application for CAAPP modification that meets the requirements of this Section
not later than 180 days before initial startup of the EGU, unless the
construction permit issued for the EGU addresses the requirements of this
Subpart B.
b) Contents of Permit Applications.
In addition to other information required for a complete application for CAAPP permit or CAAPP permit modification, the application must include the following information:
1)
The ORIS (Office of Regulatory Information Systems) or facility code assigned
to the source by the U.S. Department of Energy, Energy Information
Administration, if applicable.
2)
Identification of each EGU at the source.
3) The intended approach to the monitoring
requirements of Sections
225.240
through
225.290
of this Subpart B, or, in the alternative, the applicant may include its
intended approach to the testing requirement of Section
225.239
of this Subpart B.
4) The intended
approach to the mercury emission reduction requirements of Section
225.230
or
225.237
of this Subpart B, as applicable.
c) Permit Contents.
1) Each CAAPP permit issued by the Agency for
a source with one or more EGUs subject to the requirements of this Subpart B
must contain federally enforceable conditions addressing all applicable
requirements of this Subpart B, which conditions must be a complete and
segregable portion of the source's entire CAAPP permit.
2) In addition to conditions related to the
applicable requirements of this Subpart B, each such CAAPP permit must also
contain the information specified under subsection (b) of this
Section.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.