Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 215 - ORGANIC MATERIAL EMISSION STANDARDS AND LIMITATIONS
Subpart F - COATING OPERATIONS
Section 215.210 - Alternative Compliance Schedule
Universal Citation: 35 IL Admin Code ยง 215.210
Current through Register Vol. 48, No. 38, September 20, 2024
The owner or operator of coating lines subject to Section 215.204(d)(2) may in lieu of compliance with Section 215.211 demonstrate compliance through the use of a low solvent coating technology by taking the following actions:
a) Submit to the Agency a compliance plan, including a project completion schedule, that meets the requirements of Section 201.241 on or before August 19, 1983; and
b) Meet the following increments of progress:
1) Submit to the Agency by July 1, 1984 and
every six months thereafter a report describing in detail the progress made in
the development, application testing, product quality, customer acceptance and
United States Food and Drug Administration or government agency approval of the
low solvent coating technology;
2)
Initiate process modifications to allow the use of low solvent coatings as soon
as coatings meeting Board requirements become commercially available for
production use; and
3) Achieve
final compliance as expeditiously as possible but no later than December 31,
1986.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.