Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 204 - PREVENTION OF SIGNIFICANT DETERIORATION
Subpart B - DEFINITIONS
Section 204.630 - Repowering

Current through Register Vol. 48, No. 38, September 20, 2024

a) "Repowering" means replacement of an existing coal-fired boiler with one of the following clean coal technologies: atmospheric or pressurized fluidized bed combustion; integrated gasification combined cycle; magnetohydrodynamics; direct and indirect coal-fired turbines; integrated gasification fuel cells; or, as determined by USEPA in consultation with the U.S. Secretary of Energy, a derivative of one or more of these technologies and any other technology capable of controlling multiple combustion emissions simultaneously with improved boiler or generation efficiency and with significantly greater waste reduction relative to the performance of technology in widespread commercial use as of November 15, 1990.

b) Repowering shall also include any oil and/or gas-fired unit that has been awarded clean coal technology demonstration funding as of January 1, 1991, by the U.S. Department of Energy.

c) The Agency shall give expedited consideration to permit applications for any source that satisfies the requirements of this Section and is granted an extension under section 409 of the CAA ( 42 USC 7651h ).

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.