Section 203.203 - Construction Permit Requirement and Application

Current through Register Vol. 48, No. 38, September 20, 2024

a) A construction permit is required prior to actual construction of a major new source or major modification.

b) Applications for construction permits required under this Section shall contain sufficient information to demonstrate compliance with 35 Ill. Adm. Code 201 and the requirements of this Part including, but not limited to, Subpart C.

c) The permit shall include conditions specifying the manner in which the requirements of Subparts B and C of this Part are satisfied.

d) No permittee shall violate any condition contained in a construction permit issued for a new major stationary source or major modification which is subject to this Part.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.