Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 187 - REGULATORY INNOVATION PROJECTS
Subpart D - PROCEDURES
Section 187.402 - Development of an EMSA
Current through Register Vol. 48, No. 38, September 20, 2024
a) The Agency and the sponsor shall decide upon an acceptable development schedule for the EMSA and the proposed pilot project.
b) A sponsor shall submit to the Director a draft EMSA. At a minimum, the draft EMSA shall include:
c) Upon submittal of the initial draft EMSA, a sponsor shall provide an executive summary of the initial draft EMSA and proposed pilot project described and submitted in accordance with subsection (b) of this Section to the following persons and inform them that they may obtain the complete document from either the Agency or the sponsor:
d) A sponsor shall provide notice, by publication on a single date in a newspaper of general circulation in the area in which the proposed pilot project is located, that it has submitted an initial draft EMSA for consideration by the Agency. Such notice shall include a statement that interested persons may contact the sponsor to request that they be named to the stakeholder group in the development and implementation of the proposed pilot project. The notice shall be provided within 7 calendar days from the date the initial draft EMSA has been submitted to the Agency in accordance with subsection (b) of this Section.
e) The Agency shall give preference to and allow greater incentives in an EMSA for pilot projects that include provisions for operating sustainably through continuous improvements in products and processes. Desirable components of a pilot project include, but are not limited to, the following:
f) The Agency shall encourage the development and use of Environmental Management Systems as part of a pilot project.
g) The Agency shall reject proposed pilot projects that generate adverse environmental consequences, particularly those stimulating intermedia pollutant transfers without providing a net environmental gain.