Section 1100.405 - Standards for Denial of a Permit
Current through Register Vol. 48, No. 38, September 20, 2024
If the Agency denies any permit under this Part, the Agency must transmit to the applicant within the time limitations of this Part specific, detailed statements as to the reasons the permit application was denied. Such a statement must include, but not be limited to, the following:
a) the Sections of the Act which may be violated if the permit were granted;
b) the provisions of the regulations, promulgated under the Act, which may be violated if the permit were granted;
c) the specific type of information, if any, which the Agency deems the applicant did not provide the Agency; and
d) a statement of specific reasons why the Act and the regulations might not be met if the permit were granted. [415 ILCS 5/39] .