Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 1100 - CLEAN CONSTRUCTION OR DEMOLITION DEBRIS FILL OPERATIONS AND UNCONTAMINATED SOIL FILL OPERATIONS
Subpart B - OPERATING STANDARDS FOR CCDD FILL OPERATIONS
Section 1100.209 - Postclosure Maintenance
Current through Register Vol. 48, No. 38, September 20, 2024
The owner or operator must conduct postclosure maintenance in accordance with this Section and the Agency permit for a minimum of one year after the Agency issues a certificate of closure in accordance with Section 1100.412 unless a shorter period of time for postclosure maintenance is specified in the Agency permit. Reasons for which the Agency may specify a shorter period of time for postclosure maintenance include, but are not limited to, conformance with existing reclamation plan requirements, zoning requirements, local ordinances, private contracts, or development plans.
a) The owner or operator must remove all equipment or structures not necessary for the postclosure land use, unless otherwise authorized by the Agency permit.
b) Maintenance and Inspection of the Final Cover
c) The Agency must approve postclosure use of the property if the owner or operator demonstrates that the disturbance of the final cover will not increase the potential threat to human health or the environment.