Illinois Administrative Code
Title 35 - ENVIRONMENTAL PROTECTION
Part 105 - APPEALS OF FINAL DECISIONS OF STATE AGENCIES
Subpart D - APPEAL OF AGENCY LEAKING UNDERGROUND STORAGE TANK (LUST) DECISIONS
Section 105.406 - Extension of Time to File a Petition for Review

Current through Register Vol. 48, No. 38, September 20, 2024

Under Section 40(a)(1) of the Act, the 35-day period for petitioning for a hearing may be extended by the applicant for a period of time not to exceed 90 days by written notice provided to the Board from the applicant and the Agency within the initial appeal period. [ 415 ILCS 5/40(c)] The applicant and the Agency must jointly file a request for extension with the Board within 35 days after the date of service of the Agency's final decision. Upon an appropriately filed request for an extension, the applicant has a period not exceeding 125 days after the date of service of the Agency's final decision to file a petition for review before the Board under Section 105.408.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.