Illinois Administrative Code
Title 23 - EDUCATION AND CULTURAL RESOURCES
Part 180 - HEALTH/LIFE SAFETY CODE FOR PUBLIC SCHOOLS
Subpart C - CONSTRUCTION AND LIKE ACTIVITIES
Section 180.225 - Application for Certificate of Occupancy or Statement of Completion
Current through Register Vol. 48, No. 38, September 20, 2024
a) A school board wishing to occupy a facility subject to this Part shall make application for a Certificate of Occupancy to the regional superintendent, on a form prescribed by the regional superintendent. A board may request either a general certificate of occupancy, a certificate of partial occupancy, a certificate of occupancy for a temporary facility, or a certificate of occupancy for a vehicular facility, as applicable (see Section 180.230 ). The regional superintendent shall respond to a request for a certificate of occupancy within 20 calendar days after his or her receipt of the request.
b) When the work covered by a building permit for an existing facility is completed and the work has not affected the Certificate of Occupancy, a school district may submit a Statement of Completion in lieu of submitting an application for Certificate of Occupancy.
c) Before signing the Certificate of Occupancy or the Statement of Completion, the regional superintendent shall review any inspection statements and called inspection records, as applicable to the project. Called inspections shall be conducted and records provided by individuals qualified under Section 180.100.