a) Any property acquired or developed through assistance from the Illinois Bicycle Path Grant Program must be open to the general public for bicycle use. Property acquired or developed with program assistance may not be converted to a use which would deny bicycle use as provided by terms of the Project Agreement without prior Department approval. Approval for property conversion will be granted only if the project sponsor substitutes replacement property equal in fair market value and comparable in bicycling usefulness, quality and location.
b) Land acquired with funding assistance from the Illinois Bicycle Path Grant Program shall be operated and maintained in perpetuity for public bicycle path and recreation use.
c) For projects receiving development grant assistance only, terms of this Part shall no longer apply after the time period specified below relating to the total amount of grant funds expended on the project:
Total Grant Award |
Time Period After Final Project Billing |
$0-$50,000 |
5 years |
for every $10,000 increment over $50,000 |
add 1 year |
d) For projects receiving acquisition assistance, an appraisal must be provided by the sponsoring agency and submitted to the Department for review and certification. The appraisal must be completed to Departmental specifications. Title to any property for which grant reimbursement is sought cannot be taken by the sponsoring agency before Department approval of Certified Fair Market Value for the property is received.
e) For projects receiving development assistance, the sponsoring agency must possess either fee simple title or a permanent easement to the property being improved or an approved lease arrangement of at least 25 years, unless otherwise approved by the Department. The Department will consider, on a case-by-case basis, lease arrangements for shorter periods when State statute prohibits a unit of local government from entering into such a long-term agreement, or other circumstances beyond the control of the local unit of government prohibit such arrangements (see Section 3040.50(a)(1) ). The sponsor must also adhere to applicable state and local procurement requirements and make available to the Department all working plans, specifications, contract documents and cost estimates for review prior to commencing work. The format for any advertisement or prospectus soliciting and inviting bids, indicating dates of same, must also be presented, upon request, to the Department for review prior to publication. The Department will notify the project sponsor if the proposed project requires approval from a registered structural engineer.
f) The local sponsoring agency is required to enter into an agreement with the Department for an amount agreed upon as necessary to complete the approved project, specifying the related grant reimbursement amount and program compliance regulations.
g) Upon project completion, the project sponsor must submit a certified project billing request (expenditure statement) listing/verifying all funds expended on the project for which grant reimbursement is sought, as well as required billing documentation, as follows:
h) Financial records on approved projects must be maintained and retained by the project sponsor for possible State audit for a period of 5 years after final reimbursement payment is made by the Department.
i) The sponsoring agency must permanently post a Bicycle Path Grant Program acknowledgement sign at the project site where grant assistance is involved. The necessary sign will be provided by the Department -or specifications for its construction will be furnished to the local project sponsor, if requested.
j) Projects assisted with Illinois Bicycle Path Grant funds shall be implemented in accordance with all applicable federal, State and local laws, ordinances and regulations relating to public agency expenditure of funds for public works projects.
k) It shall be understood by the project sponsor that a Department representative may make periodic inspections of the project as construction progresses and that a final inspection and acceptance of the completed project must be made by a representative or agent of the Department prior to final payment of grant reimbursement to the local sponsoring agency.
l) The sponsoring agency shall indemnify, protect, defend and hold harmless the Department from any and all liability, costs, damages, expenses, or claims thereof arising under, through or by virtue of the construction, operation and maintenance of Program-assisted bicycle path facilities.
m) In connection with and prior to the construction, and thereafter the subsequent operation and maintenance of Program-assisted bicycle facilities, it shall be understood that the project sponsor is responsible for obtaining any and all necessary construction permits, licenses or forms of consent as may be required by law. Failure to obtain any required permit(s) may jeopardize approved grant funding.
n) The sponsoring agency must comply with and abide by the following operation and maintenance provisions:
o) Conflict of Interests
p) The Project Sponsor certifies that it provides a drug free workplace and related employee assistance as defined and required by the Drug Free Workplace Act [30 ILCS 105/16 ].
q) Pursuant to 775 ILCS 5/2-105(A)(4), the Project Sponsor certifies that it has a written sexual harassment policy that includes, at a minimum, the following information:
r) Program Violations and Project Termination