Idaho Administrative Code
Title IDAPA 58 - Environmental Quality, Department of
Rule 58.01.25 - RULES REGULATING THE IDAHO POLLUTANT DISCHARGE ELIMINATION SYSTEM PROGRAM
Section 58.01.25.107 - DECISION PROCESS

Universal Citation: ID Admin Code 58.01.25.107

Current through August 31, 2023

After the Department has determined that a permit application is complete the Department will decide whether to tentatively deny the application, or prepare an IPDES draft permit. (3-24-22)

01. Application Denial. If the Department decides to tentatively deny the application: (3-24-22)

a. A notice of intent to deny the permit application shall be issued. A notice of intent to deny the permit application is a type of draft permit which follows the same procedures as any draft permit and shall be made available for public comment, and the Department shall give notice of opportunity for a public meeting, as specified in Section 109 (Public Notification and Comment); (3-24-22)

b. The Department shall generate a response to public comment; and (3-24-22)

c. Issue a final decision. The final decision may: (3-24-22)
i. Be to withdraw the notice of intent to deny the application, and proceed to prepare a draft permit and fact sheet as defined in Section 108 (Draft Permit and Fact Sheet); or (3-24-22)

ii. Confirm the decision to deny the application. (3-24-22)

d. The applicant may appeal the final decision to deny the application by adhering to the requirements of Section 204 (Appeals Process). (3-24-22)

02. Draft Permit. If the Department decides to generate a draft permit and fact sheet it will comply with Section 108 (Draft Permit and Fact Sheet). (3-24-22)

a. Upon completion of the draft permit and fact sheet the Department shall issue a public notification as required in Subsection 109.01. (3-24-22)

b. An opportunity for the public to comment and request a public meeting shall be provided. (3-24-22)

c. The Department shall generate a response to public comment as stipulated in Subsection 109.03. (3-24-22)

03. Proposed Permit. After the close of the public comment period on a draft permit, the Department will make appropriate changes in response to comments, and generate a proposed permit and fact sheet. (3-24-22)

04. Final Permit. After the close of the public comment period on a draft permit, and after receipt of comments on the proposed permit, if any, from EPA, the Department shall issue a final permit decision and fact sheet. A final permit decision means a final decision to issue, deny, modify, revoke and reissue, or terminate a permit. (3-24-22)

a. The Department shall notify the applicant and each person who has submitted written comments or requested notice of the final permit decision. (3-24-22)

b. A final permit decision shall become effective twenty-eight (28) days after the service of notice of the decision unless: (3-24-22)
i. A later effective date is specified in the decision; or (3-24-22)

ii. A Petition for Review is filed with the Department as specified in Section 204 (Appeals Process). (3-24-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.