The Department will not issue an IPDES permit for a discharge: (3-24-22)

01. Clean Water Act Compliance. Unless the conditions of the permit provide for compliance with the applicable requirements of IDAPA 58.01.02, "Water Quality Standards" and 58.01.25 "Rules Regulating the Idaho Pollutant Discharge Elimination System Program"; (3-24-22)

02. EPA Objection. When the Department has received written objection pursuant to 40 CFR 123.44 from the EPA Regional Administrator to issuance of the permit and until the objections are resolved according to the process identified in the Memorandum of Agreement between EPA and the Department; (3-24-22)

03. Water Quality Requirements. When the imposition of conditions cannot ensure compliance with the applicable water quality requirements of all affected states; (3-24-22)

04. Anchorage and Navigation Impaired. When, in the judgment of the Secretary of the United States Army through the Army Corp Chief of Engineers, anchorage and navigation in or on any of the waters of the United States would be substantially impaired by the discharge; (3-24-22)

05. Banned Content. Of any radiological, chemical, or biological warfare agent or high level radioactive waste; (3-24-22)

06. Area Wide Waste Treatment Management Plans. That is inconsistent with a plan or plan amendment approved under the Clean Water Act section 208(b); or (3-24-22)

07. New Sources or New Dischargers. For a new source or new discharger, if the discharge from its construction or operation will cause or contribute to the violation of water quality standards. (3-24-22)

a. When the owner or operator of a new source or new discharge proposes to discharge into a water segment that does not meet applicable water quality standards, or that is not expected to meet those standards even after the application of the effluent limitations required by Clean Water Act sections 301(b)(1)(A) and (B), and for which the state or interstate agency has performed a pollutant load allocation for the pollutant to be discharged, then the owner or operator must demonstrate that: (3-24-22)
i. There are sufficient remaining pollutant load allocations to allow for the discharge; and (3-24-22)

ii. The existing dischargers into that segment are subject to compliance schedules designed to bring the segment into compliance with applicable water quality standards. (3-24-22)

b. The Department may waive the submission of the information by the permit applicant required in Subsection 103.07.a. if the Department determines that it already has adequate information to evaluate the request. (3-24-22)

c. An explanation of the development of limitations to meet the criteria of this section is to be included in the fact sheet to the permit. (3-24-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.