Idaho Administrative Code
Title IDAPA 58 - Environmental Quality, Department of
Rule 58.01.13 - RULES FOR ORE PROCESSING BY CYANIDATION
Section 58.01.13.502 - DECISION TO APPROVE OR DISAPPROVE OF A PERMANENT CLOSURE REPORT
Current through August 31, 2023
01. Cost Recovery. Final closure of the cyanidation facility will not be approved if any payment required by the cost recovery agreement under Subsection 100.04 is due and unpaid. (3-24-22)
02. Issuance of Director's Determination. Within sixty (60) days of receipt of a permanent closure report, the Director will issue to the permittee a Director's determination of approval or disapproval of the permanent closure report. The Director's determination will be based on applicable statutes or rules administered by the Department. The Department will coordinate the evaluation of the permanent closure report with the Idaho Department of Lands. (3-24-22)
03. Director's Determination to Disapprove a Permanent Closure Report. A Director's determination to disapprove a permanent closure report will specifically identify and discuss those reasons for disapproval, any administrative actions being considered by the Director, and the permittee's options and procedures for administrative appeal. The Director's determination to disapprove a permanent closure report must include: (3-24-22)