Section 58.01.13.500 - PERMIT CONDITIONS
Current through August 31, 2023
The following conditions apply to and must be specified in all permits: (3-24-22)
01. Compliance Required. The applicant or permittee must comply with all conditions of the permit. Issuance or possession of a permit issued according to these rules does not relieve the applicant or permittee of the responsibility to comply with all other applicable local, state, and federal laws. (3-24-22)
02. Construction. Construction of individual components of a cyanidation facility may commence upon approval by the Department of the final plans and specifications for that component. (3-24-22)
03. Record Plans and Specifications. An Idaho licensed professional engineer must confirm in writing that all record drawings and specifications are complete and accurate. These record plans and specifications must be submitted by the permittee to the Director within thirty (30) days after the completion of the construction of each critical phase of facility development as approved by the Department. The record plans and specifications must be accompanied by a final construction report. If the construction does not deviate from the approved plans and specifications, a statement to the effect must be submitted by the engineer. The Department will review the final construction report, including record plans and specifications and results of quality control and quality assurance testing, to verify that the facility was constructed in compliance with and does not deviate from the approved plans and specifications. If the Department determines that the facility was not constructed in compliance with or deviates from the approved plans and specifications, the Department will provide the permittee written notice of necessary corrective actions within thirty (30) days of receipt of all submittals required by this subsection. In the event the Department provides such written notice, operation of the facility may not begin until the Department inspects and provides written approval of the corrective actions. Operation of the facility may begin if the Department does not deliver to the permittee such written notice within thirty (30) days of receipt of all submittals required by this subsection. (3-24-22)
04. Duty to Provide Information. The permittee must furnish to the Director, within a reasonable or specified time, any information, including copies of records required by the permit or other applicable rules, that the Director may request to determine whether cause exists for modifying or revoking the permit or to determine compliance with the permit or other applicable rules. (3-24-22)
05. Notifications. After initial construction and seasonal and/or temporary closure, the permittee must, within thirty (30) days, provide written notice to the Director of the permittee's intentions to commence or restart operations. At least thirty (30) days prior to completion of operations, and/or temporary or seasonal operations, the permittee must notify the Director of the permittee's intentions to temporarily, seasonally or permanently close operations. Notification must provide sufficient time for the Director to provide pre-operational or post-operational inspections, as necessary. (3-24-22)
06. Entry and Access. The permittee must allow the Director, or a designee obligated by agreement with the Director to comply with the confidentiality provisions of Section 39-111, Idaho Code, to: (3-24-22)
07. Reporting. It is the permittee's responsibility to report to the Director: (3-24-22)
08. Discharge Response. If an unauthorized discharge occurs the permittee must implement the Department approved emergency and spill response plan. (3-24-22)
09. Temporary or Seasonal Closure Plans. Prior to temporary or seasonal closure, the permittee must submit a temporary or seasonal closure plan to the Director for approval. The plan must describe the procedures, methods, and schedule to be implemented for the treatment and disposal of process water and pollutants, the control of drainage from the cyanidation facility, the control of drainage from the surrounding area, and the secure storage of chemicals during the period of closure. Within thirty (30) days of receiving the plan, the Director will approve and/or suggest modifications necessary to protect waters. The permittee must ensure that closure complies with an approved plan. The approved plan must be implemented before the permittee completes temporary or seasonal closure. Facilities may not be temporarily or seasonally closed for a period longer than two (2) years unless approved by the Director. (3-24-22)
10. Begin Construction. If the permittee fails to begin construction of a cyanidation facility within one (1) year of the effective date of the permit, the permit will be deemed void. (3-24-22)
11. Permanent Closure. The permanent closure plan, as approved by the Idaho Department of Lands, will be incorporated by reference into the Department-issued permit as a permit condition and will be enforceable as such. (3-24-22)