Idaho Administrative Code
Title IDAPA 58 - Environmental Quality, Department of
Rule 58.01.03 - INDIVIDUAL/SUBSURFACE SEWAGE DISPOSAL RULES AND RULES FOR CLEANING OF SEPTIC TANKS
Section 58.01.03.011 - INSPECTIONS

Universal Citation: ID Admin Code 58.01.03.011

Current through August 31, 2023

01. One or More Inspections Required. Such inspection as are necessary to determine compliance with any requirement or provision of these rules shall be required by the Director. (3-31-22)

02. Duty to Uncover. The permittee shall, at the request of the Director, uncover or make available for inspection any portion or component of an individual or subsurface sewage disposal system which was covered or concealed in violation of these rules. (3-31-22)

03. Advance Notice by Permittee. If an inspection requires some type of preparation, such as test hole excavation or partial construction of the system, the applicant or permittee will notify the Director at least forty-eight (48) hours in advance, excluding weekends and holidays, before the time preparation will be completed. (3-31-22)

04. Substantiating Receipts and Delivery Slips. The permittee shall upon request by the Director provide copies of receipts, delivery slips or other similar documents to substantiate the origin, quality, or quantity of materials used in the construction of any individual or subsurface system. (3-31-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.