Idaho Administrative Code
Title IDAPA 58 - Environmental Quality, Department of
Rule 58.01.01 - RULES FOR THE CONTROL OF AIR POLLUTION IN IDAHO
Section 58.01.01.365 - PREPARATION OF PROPOSED PERMIT OR PROPOSED DENIAL

Universal Citation: ID Admin Code 58.01.01.365

Current through August 31, 2023

01. Timeline. Except as otherwise provided by these rules, the Department will prepare a proposed permit or proposed denial within thirty (30) days after the close of the public comment period, unless the Department determines that additional time is required to evaluate comments and information received. (3-28-23)

02. Availability. The proposed permit or proposed denial will be available to the public upon the filing a written public documents request and the payment of any costs. (3-28-23)

03. Notice to Affected States. If the Department refuses to accept all recommendations that an affected State submitted during the public comment period, the Department will send a copy of the notice sent to EPA in accordance with Subsection 366.01.d. to the affected State that submitted the recommendation. (3-28-23)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.