Idaho Administrative Code
Title IDAPA 39 - Transportation, Department of
Rule 39.03.42 - RULES GOVERNING HIGHWAY RIGHT-OF-WAY ENCROACHMENTS ON STATE RIGHTS-OF-WAY
Section 39.03.42.201 - PERMIT COMPLIANCE AND EXPIRATION

Universal Citation: ID Admin Code 39.03.42.201

Current through August 31, 2023

01. Permitted Work. If work does not begin immediately, the permittee shall notify the Department or local highway agency five (5) working days prior to commencing such work. Local highway agency shall promptly notify the Department, when applicable. (3-31-22)

02. Work Site Documents. The permittee or contractor for the permittee, shall maintain a copy of the approved permit, all special provisions and any related documents, at the work site while work is in progress. (3-31-22)

03. Completion of Work. All permitted work shall be completed and available for final inspection within thirty (30) days after construction begins, unless otherwise stated in the special provisions of the permit. If the permitted work is not completed within one (1) year of permit issuance, the permit shall be considered void. At the discretion of the Department, a one-time extension not to exceed six (6) months may be granted if requested in writing by the permittee prior to permit expiration. New applications shall be required for additional work following permit expiration. (3-31-22)

04. Temporary Encroachments. Temporary encroachment permits shall have an effective time period not to exceed one (1) calendar year and shall be removed within ten (10) days following permit expiration. (3-31-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.