Idaho Administrative Code
Title IDAPA 37 - Water Resources, Department of
Rule 37.03.05 - MINE TAILINGS IMPOUNDMENT STRUCTURES RULES
Section 37.03.05.010 - DEFINITIONS
Current through September 2, 2024
Unless the context otherwise requires, the following definitions govern these rules.
01. Board. The Idaho Water Resource Board.
02. Director. The Director of the Idaho Department of Water Resources.
03. Department. The Idaho Department of Water Resources.
04. Mine Tailings Impoundment Structure. Any artificial embankment which is or will be more than thirty (30) feet in height measured from the lowest elevation of the toe to the maximum crest elevation constructed for the purpose of storing mine tailings slurry.
05. Mine Tailings Slurry. All slurry wastes from a mineral processing or mining operation.
06. Mine Tailings Storage Capacity. The total storage volume of the impoundment when filled with tailings to the maximum approved design storage elevation.
07. Borrowed Fill Embankment. Any embankment constructed of borrowed earth materials and which is designed for construction by conventional earth moving equipment.
08. Reservoir. Any basin which contains or will contain the material impounded by the mine tailings impoundment structure.
09. Owner. Includes any of the following who own, control, operate, maintain, manage, or propose to construct a mine tailings impoundment structure or reservoir.
10. Alterations, Repairs or Either of Them. Only such alterations or repairs as may directly affect the safety of the mine tailings impoundment structure or reservoir, as determined by the Director.
11. Enlargement. Any change in or addition to an existing mine tailings impoundment structure or reservoir, which raises or may raise the storage capacity of the structure, as defined in Rule Subsection 010.06.
12. Days Used in Establishing Deadlines. Calendar days including Sundays and holidays.
13. Certificate of Approval. A certificate issued by the Director for the mine tailings impoundment structure listing restrictions imposed by the Director, and without which no new mine tailings impoundment structures shall be allowed to impound mine tailings slurry or water and no existing impoundment shall be allowed to impound water or continue deposition of mine tailings slurry. The structure will be recertified following the site inspection scheduled according to the Hazard Classification assigned by the Department, unless the Director determines that the structure is unsafe.
14. Engineer. A registered professional engineer, licensed as such by the state of Idaho.
Effective March 30, 2023