Idaho Administrative Code
Title IDAPA 24 - Occupational and Professional Licenses, Division of
Rule 24.39.31 - RULES FOR FACTORY BUILT STRUCTURES
Section 24.39.31.500 - PERMITS, PLAN REVIEWS, AND INSPECTIONS
Current through September 2, 2024
01. Modular Building Permit Fees. Permits must be obtained from the Division prior to the construction of structures governed by 39-4303, Idaho Code. Other than as specified in this section, the permit fee schedule for Modular Buildings is as provided in Table 1-A plus ninety dollars ($90) and two and one-half percent (2.5%) of the plumbing, electrical, and HVAC installation costs. The determination of value or valuation is based on the total value of all construction work for which a permit is issued.
TABLE 1-A - MODULAR BUILDING PERMIT FEES |
|
TOTAL VALUATION |
FEE |
$1 to $500 |
= $23.50 |
$501 to $2,000 |
= $23.50 for the first $500 plus $3.05 for each additional $100, or fraction thereof, to and including $2,000 |
$2,001 to $25,000 |
= $69.25 for the first $2,000 plus $14 for each additional $1,000, or fraction thereof, to and including $25,000 |
$25,001 to $50,000 |
= $391.75 for the first $25,000 plus $10.10 for each additional $1,000, or fraction thereof, to and including $50,000 |
$50,001 to $100,000 |
= $643.75 for the first $50,000 plus $7 for each additional $1,000, or fraction thereof, to and including $100,000 |
$100,001 to $500,000 |
= $993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof, to and including $500,000 |
$500,001 to $1,000,000 |
= $3,233.75 for the first $500,000 plus $4.75 for each additional $1,000, or fraction thereof, to and including $1,000,000 |
$1,000,001 and up |
= $5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000, or fraction thereof |
02. Modular Plan Review. The Modular Building fee includes an additional amount equal to sixty-five percent (65%) of the permit fee calculated in accordance with Table 1-A. A fee of sixty-five dollars ($65) per hour applies to additional plan review required by changes, additions, or revisions to plans.
03. Manufactured/Mobile Home Installation Permit Fees. Permits must be obtained from the Division prior to the site installation governed by 44-2202, and 39-4004, Idaho Code in accordance with the following schedule:
04. In-Plant Inspection Agency Fees. In-plant inspection fees for manufactured homes produced by Idaho Manufactures as per 39-4003A and 39-4004 of Idaho Code is set at forty-five dollars ($45) per floor.
05. Inspections at Manufacturing Plants. The Division conducts inspections at the manufacturing plant to determine compliance with codes adopted by Title 39, Chapters 40 and 41, Idaho Code, and Title 54, Chapters 10, 26, and 50, Idaho Code.
06. Manufactured Home Site Installation Inspections. Installation permits must be obtained from the Division for installations in areas where there is no approved local program, or from a city or county that has by ordinance adopted building codes pursuant to Section 39-4116, Idaho Code, and whose installation program has been approved by the Division. All installations must be inspected and approved by the authority having jurisdiction before the manufactured home is occupied.
07. Modular Site Installation Inspection. In order to complete the installation of an Idaho approved Modular Building, approval and inspection of the installation by the enforcement agency having jurisdiction over the site location is required.
08. Qualifications of Inspectors. All inspectors must be properly certified for the type of inspection Certification Program Construction Code Inspector program (NCPCCI), the National Inspection Testing Certification program (NITC), the International Association of Electrical Inspectors (IAEI), and the International Code Council (ICC).
09. Minimum Training Requirements for Inspectors. All manufactured home installation inspectors must complete eight (8) hours of training or instruction germane to the profession.
10. Rights and Limitations of Local Enforcement Agencies for Modular Buildings.
11. Division Approval. A city or county that has by ordinance adopted a building code pursuant to Section 39-4116, Idaho Code, is eligible to participate in the inspection of manufactured and mobile homes. Such local installation inspection program must be approved by the Division to provide inspection services if the following minimum criteria is met:
12. Modular Insignia and Serial Number.
Effective July 1, 2024