Idaho Administrative Code
Title IDAPA 20 - Lands, Department of
Rule 20.03.03 - RULES GOVERNING ADMINISTRATION OF THE RECLAMATION FUND
Section 20.03.03.018 - ACREAGE AND RECLAMATION COST LIMITATIONS

Universal Citation: ID Admin Code 20.03.03.018

Current through August 31, 2023

01. Actual Allowable Participation. The Board will establish by policy the actual allowable disturbance, actual allowable reclamation cost, and the minimum dollar per acre of disturbance in order to provide financial assurance to opt out of participation in the Reclamation Fund. (3-18-22)

02. Maximum Disturbance and Reclamation Cost. The maximum disturbance and maximum reclamation costs in these rules are maximums. The maximum allowable disturbance is eighty (80) acres; the maximum allowable reclamation cost is four hundred forty thousand dollars ($440,000). (3-18-22)

03. Multiple Plans or Permits. An operator who has multiple mining reclamation plans or permits that have a total disturbance in excess of the actual allowable disturbance, or with total reclamation costs in excess of the actual allowable reclamation cost, may participate in the Reclamation Fund with one (1) or more sites that together contain less than both of the Board-established actual allowable limits. (3-18-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.