01. Unforeseen Events. If a mining operator finds that unforeseen events or unexpected conditions require immediate change from an approved plan, the operator may continue mining in accordance with the procedures dictated by the changed conditions, pending submission and approval of an amended plan, even though operations do not comply with the approved reclamation plan on file with the Department. This shall not excuse the operator from complying with the requirements of Sections 140 and 120 of these rules. (3-18-22)

02. Notification. The operator shall notify the director, in writing, within ten (10) days of the discovery of conditions that require deviation from the approved plan. A proposed amendment to the reclamation plan must be submitted by the operator within thirty (30) days of the discovery of those conditions. (3-18-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.