Idaho Administrative Code
Title IDAPA 20 - Lands, Department of
Rule 20.03.01 - RULES GOVERNING DREDGE AND PLACER MINING OPERATIONS IN IDAHO
Section 20.03.01.022 - PROCEDURES FOR REVIEW AND DECISION UPON AN APPLICATION

Universal Citation: ID Admin Code 20.03.01.022

Current through August 31, 2023

01. Decision on Application. Following the Director's review of an application for a new permit, or to amend an existing permit and provide an opportunity to correct any deficiencies, the Board will approve or disapprove the application and the Director will notify the applicant of the Board's decision by mail. Such notice will contain any reservations conditioned with the approval, or the information required to be given under Subsections 022.07 and 022.09 if disapproved. If approved, a permit will be issued after the bonding requirements of Section 035 are met. No mining is allowed until the permit is bonded and applicant is notified by mail or telephone of approval. (3-18-22)

02. Public Hearings. For the purpose of determining whether a proposed application complies with these rules, the Director may call for a public hearing, as described in Section 030. (3-18-22)

03. Adverse Weather. If weather conditions prevent the Director from inspecting the proposed mining site to acquire the information required to evaluate the application, the application may be placed in suspense, pending improved weather conditions. The applicant will be notified in writing of this action. (3-18-22)

04. Interagency Comment. Nonconfidential materials submitted under Section 021 will be forwarded by the Director to the Departments of Water Resources, Environmental Quality, and Fish and Game for review and comment. If operations are to be located on federal lands, the department will notify the U. S. Bureau of Land Management or the U.S. Forest Service. The Director may provide public notice on receipt of a reclamation plan. In addition, a copy of an application will be provided to individuals who request the information in writing, subject to Title 74, Chapter 1, Idaho Code. (3-18-22)

05. Stream Alteration Permits. No permit will be issued proposing to alter, occupy or to dredge any stream or watercourse without notification to the Department of Water Resources of the pending application. The Department of Water Resources will respond to said notification within twenty (20) days. If a stream channel alteration permit is required, it must be issued prior to issuance of the placer and dredge permit. (3-18-22)

06. Water Clarification. No permit will be issued until the Director is satisfied that the methods of water clarification proposed by the applicant are of sound engineering design and capable of meeting the water quality standards established under Title 39, Chapter 1, Idaho Code, and IDAPA 58.01.02, "Water Quality Standards," IDAPA, 58.01.11. "Ground Water Quality Rule." (3-18-22)

07. Permit Denial Authority. The Board has the power to deny any application for a permit on state lands, streams, or riverbeds, or on any unpatented mining claims, upon its determination that a placer or dredge mining operation on the area proposed would not be in the public interest, giving consideration to economic factors, recreational use for such lands, fish and wildlife habitat, and other factors which in the judgement of the Board may be pertinent, and may deny any application upon notification by the Department of Water Resources that the granting of such permit would result in permanent damage to the stream channel. (Section 47-1317(j), Idaho Code) (3-18-22)

08. Permit Conditions. If an application fails to meet the requirements of these rules, the Board may issue a permit subject to conditions that bring the application into compliance with these rules. The applicant may accept or refuse the permit. Refusal to accept the permit is considered a denial under Subsection 022.09. (3-18-22)

09. Amended Applications. If the Board disapproves the application, the applicant will be informed of the rules that have not been complied with, the manner in which they have not been complied with, and the requirements necessary to correct the deficiencies. The applicant may then submit an amended application, which will be processed as described in Section 022. (3-18-22)

10. Permit Offering. Upon approval by the Board, the applicant will be notified of the action and the amount of bond required. Upon receipt of the required bond, the permit will be sent to the applicant for signature. If the bond and the permit, signed by the applicant, are not received within twelve (12) months of Board action, the approval will be automatically rescinded, except that upon written request of the applicant, and for good cause, the Director may defer decision of the Board's approval for a reasonable period of time not to exceed one (1) year. The Director will notify the applicant of his decision in writing. (3-18-22)

11. Reclamation Obligations. The permit issued by the Board governs and determines the nature and extent of the reclamation obligations of the Permittee. (3-18-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.