Idaho Administrative Code
Title IDAPA 02 - Agriculture, Department of
Rule 02.02.12 - BONDED WAREHOUSE RULES
Section 02.02.12.501 - NPE CONTRACT CLAIMS ON THE FUND

Universal Citation: ID Admin Code 02.02.12.501

Current through August 31, 2023

NPE contracts shall be executed in writing, dated, and signed by all parties to the contract. (3-15-22)

01. NPE Clause. An NPE contract shall have the following statement: "No claim shall be paid from the CIF pursuant to Section 69-263, Idaho Code, if a producer files his claim more than one hundred eighty (180) days from the date the contract is executed." (3-15-22)

02. NPE Contract List. A warehouseman shall maintain a list of all NPE contracts written in a calendar year that reflects the producers name, contract number, agricultural commodity, and date of the contract. (3-15-22)

03. NPE Contract Renewal Period. A producer may renew an NPE contract; but no claim shall be paid from the CIF if a producer files his claim more than three hundred sixty-five (365) days from the date the original NPE contract was executed. (3-15-22)

Disclaimer: These regulations may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.