NPE contracts shall be executed in writing, dated, and signed by all parties to the contract. (3-15-22)
01. NPE Clause. An NPE contract shall have the following statement: "No claim shall be paid from the CIF pursuant to Section 69-263, Idaho Code, if a producer files his claim more than one hundred eighty (180) days from the date the contract is executed." (3-15-22)
02. NPE Contract List. A warehouseman shall maintain a list of all NPE contracts written in a calendar year that reflects the producers name, contract number, agricultural commodity, and date of the contract. (3-15-22)
03. NPE Contract Renewal Period. A producer may renew an NPE contract; but no claim shall be paid from the CIF if a producer files his claim more than three hundred sixty-five (365) days from the date the original NPE contract was executed. (3-15-22)