(a) Except as provided in subsection (b), each imperfection or damage that impairs the serviceability of a segment of steel transmission line operating at or above forty percent of SMYS must be repaired as follows:
(1) If it is feasible to
take the segment out of service, the imperfection or damage must be removed by
cutting out a cylindrical piece of pipe and replacing it with pipe of similar
or greater design strength;
(2) If
it is not feasible to take the segment out of service, a full encirclement
welded split sleeve of appropriate design must be applied over the imperfection
or damage; and
(3) If the segment
is not taken out service, the operating pressure must be reduced to a safe
level during the repair operations.
(b) Submerged offshore pipelines and submerged pipelines in inland navigable waters may be repaired by mechanically applying a fully encirclement split sleeve of appropriate design over the imperfection or damage.
Disclaimer: These regulations may not be the most recent version. Hawaii may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.