Except for service lines and plastic pipelines, each segment of a pipeline that is to be operated at a hoop stress less than thirty percent of SMYS and at or above 100 p.s.i.g. must be tested in accordance with the following:
(1) The pipeline operator must use a test procedure that will ensure discovery of all potentially hazardous leaks in the segment being tested;
(2) If, during the test, the segment is to be stressed to twenty percent or more of SMYS and natural gas, inert gas, or air is the test medium:
(A) A leak test must be
made at a pressure between 100 p.s.i.g. and the pressure required to produce a
hoop stress of 20 percent of SMYS; or
(B) The line must be walked to check for
leaks while the hoop stress is held at approximately twenty percent of
SMYS;
(3) The pressure must be maintained at or above the test pressure for at least one hour.
Disclaimer: These regulations may not be the most recent version. Hawaii may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.