Hawaii Administrative Rules
Title 12 - DEPARTMENT OF LABOR AND INDUSTRIAL RELATIONS
Subtitle 8 - HAWAII OCCUPATIONAL SAFETY AND HEALTH DIVISION
Part 10 - PRESSURE RETAINING ITEMS
Chapter 224.1 - PRESSURE VESSELS
Section 12-224.1-5 - Technical installation requirements
Current through November, 2024
(a) All pressure vessels shall be installed as required in section 12-220-2.1 and this chapter. An application for installation permit shall be submitted to the department prior to the commencement of work. Pressure vessels installed without an installation permit may be subject to citations with penalties up to $10,000 per day pursuant to section 12-220-22.
(b) First acceptance inspection and certification. The following shall apply to first acceptance inspections and certifications:
(c) Clearances. All pressure vessel installations must allow sufficient clearance for normal operation, maintenance, and inspection (internal and external). Except as otherwise authorized by the department, clearances for pressure vessels shall not be less than three (3) feet where inspection openings are provided. Vessels having manholes shall have five (5) feet clearance from the manhole opening and any wall, ceiling, or piping that may prevent a person from entering. All other sides shall not be less than eighteen (18) inches between the vessel and adjacent walls or other structures. Alternative clearances in accordance with the manufacturer's recommendations are subject to acceptance by the department.
(d) Pressure relief devices. All pressure vessels shall be protected by pressure relief devices in accordance with the following requirements:
(e) Supports. Pressure vessels and associated piping shall be safely supported. The potential for future pressure tests of the vessel after installation shall be considered when designing vessel supports. Design of supports, foundations, and settings shall consider vibration (including seismic and wind loads where necessary), movement (including thermal expansion and contraction), grounding/bonding to minimumize electrolytic corrosion, and loadings (including the weight of water during a pressure test) in accordance with department requirements, manufacturer's recommendations, and other industry standards, as applicable.
(f) Piping. Piping loads on the vessel nozzles shall be considered. Piping loads include weight of the pipe, weight of the contents of the pipe, and expansion of the pipe from temperature and pressure changes (wind and seismic loads). The effects of piping vibration on the vessel nozzles shall also be considered.
(g) Bolting. All mechanical joints and connections shall conform to the manufacturers' installation instructions and recognized standards acceptable to the jurisdiction.
(h) Instruments and controls. The following shall apply to the instruments and controls of pressure vessels:
(i) Isolating valves. Each pressure vessel or multiple pressure vessels connected in series shall have isolating valves which isolate the vessel or vessels from the system in which it or they are installed.
(j) Additional requirements for compressed air vessels. The following shall apply to compressed air vessels:
(k) Additional requirements for hot water storage tanks. The following shall apply to hot water storage tanks:
(l) Additional requirements for tanks and heat exchangers include the following:
(m) Description and concerns of specific types of pressure vessels.
Pressure relief devices must have a_quick opening manual shutoff valve installed between the chamber and the pressure relief device, with a frangible seal in place, within easy access to the operator. The pressure relief device shall be constructed in accordance with ASME BPVC Section VIII. The discharge from the pressure relief device must be piped outside to a safe point of discharge. Rupture disks may be used only if they are in series with a pressure relief valve, or when there is less than two (2) cubic feet of water volume. Verify that the safety valve is periodically tested either manually by raising the disk from the seat or by removing and testing the valve on a test stand.