Hawaii Administrative Rules
Title 12 - DEPARTMENT OF LABOR AND INDUSTRIAL RELATIONS
Subtitle 8 - HAWAII OCCUPATIONAL SAFETY AND HEALTH DIVISION
Part 10 - PRESSURE RETAINING ITEMS
Chapter 222.1 - POWER BOILERS
Section 12-222.1-5 - Technical installation requirements
Universal Citation: HI Admin Rules 12-222.1-5
Current through January, 2025
(a) General requirements. The following shall apply to all power boilers:
(1) Power boilers shall be installed pursuant
to section
12-220-2.1 and this
chapter;
(2) Owners and users shall
adhere to the power boiler installation requirements as specified in NBIC Part
1, and this chapter;
(3) An
application for installation permit shall be submitted to the department prior
to commencement of work;
(4)
Boilers installed without an installation permit may be subject to citation and
penalties of up to $10,000 per day pursuant to section
12-220-22;
(5) Only contractors holding a valid Hawaii
C-4 contractor license issued by the contractors license board of the
department of commerce and consumer affairs shall install power boilers;
and
(6) All power boilers shall be
equipped with controls and safety devices based upon the Btu/hr burner input,
as specified in the original code of construction, and in accordance with the
following codes and standards:
(A) Boilers
with energy input ratings of less than 12,500,000 Btu/hr shall meet the
requirements of ASME CSD-1;
(B)
Boilers with energy input ratings of 12,500,000 Btu/hr and above shall meet the
requirements of NFPA-85;
(C) All
atmospheric fluidized bed boilers, boilers with pulverized fuel systems, and
boilers that are stoker fired shall meet the requirements of NFPA-85;
and
(D) No new miniature boiler
shall be installed unless it has been constructed and inspected to ASME BPVC
standards, bears the ASME certification mark with the "S", "M", or "E"
designator in accordance with the requirements of Part PMB of ASME BPVC Section
I, and when required, has controls and safety devices installed that are in
accordance with ASME CSD-1.
(b) First acceptance inspection and certification requirements shall include the following:
(1) The owner, user, and contractor shall
comply with section
12-220-2.1, and upon completion of
the installation shall arrange for an acceptance inspection by the
department;
(2) The installing
contractor shall operationally test the boiler controls and safety devices
prior to scheduling the first acceptance inspection with the department and
record the results on form CG-500, ASME CSD-1, and file a copy with the
department;
(3) First inspections
for power boilers shall include internal inspection, pressure test, and
operational testing of the controls and safety devices;
(4) The installing contractor shall test the
boiler as directed and witnessed by an inspector employed by the
department;
(5) An inspector
employed by the department shall conduct the first data inspection, acceptance,
and mark the state serial number on the power boiler pursuant to section
12-220-29.1. Power boilers may not
be placed into service until its installation has been inspected and accepted
by the department;
(6) The
installer shall complete and certify the NBIC Boiler Installation Report I-1,
(NB-365, see Exhibit 3, titled, "Boiler Installation Report I-1", dated October
1, 2023, which is made a part of this chapter and located at the end of this
chapter) after the completion, inspection, and acceptance of the installation.
The report shall be submitted to the owner and the department;
(7) The installer shall exercise care during
installation to prevent loose weld material, welding rods, small tools, and
miscellaneous scrap metal from getting into the vessel. Prior to making the
final closure, the installer shall inspect the interior of the vessel and its
appurtenances for the presence of foreign debris, and if present the debris
shall be removed;
(8) Subject to
department requirements, a leak test may be performed on any components whose
pressure test is not documented under the items' Manufacturer's Data Report.
This leak test should not exceed 90 per cent of the lowest pressure relief
device setpoint. The test data shall be recorded, and the data made available
as required; and
(9) All fuel fired
boiler and fuel fired pressure vessel combustion air-fuel ratios shall be
analyzed, adjusted, and values documented during commissioning to meet emission
requirements of the department and limits of the manufacturer, as
required.
(c) The following shall apply to power boiler clearances:
(1) Boiler installations shall allow for
normal operation, maintenance, and inspections. There shall be at least
thirty-six (36) inches of clearance on each side of a boiler to enable access
for maintenance and inspection activities. Boilers operated in battery shall
not be installed closer than forty-eight (48) inches from each other. The front
or rear of any boiler shall not be located closer than thirty-six (36) inches
from any wall or structure;
(2)
Alternative clearances in accordance with the manufacturer's recommendations
are subject to acceptance by the department;
(3) Boilers shall be installed to allow for
removal and installation of tubes;
(4) Boilers with a top-opening manhole shall
have at least eighty-four (84) inches of unobstructed clearance above the
manhole to the ceiling of the equipment room; other manhole openings shall have
at least five (5) feet; and
(5)
Boilers with a bottom opening used for inspection or maintenance shall have at
least twelve (12) inches of unobstructed clearance.
(d) The following shall apply to electric and miniature boiler clearances:
(1) Electric and
miniature boilers shall be installed at an accessible location for inspection
and maintenance;
(2) Electric and
miniature boilers shall not be installed in ceilings unless provided with
permanent ladders, floors, and height clearance for safe access;
(3) Control sides and door openings shall
have three (3) feet clearance from any type of interference;
(4) All other sides shall have eighteen (18)
inches of clearance; and
(5)
Alternative clearances in accordance with the manufacturer's recommendations
are subject to acceptance by the department.
Disclaimer: These regulations may not be the most recent version. Hawaii may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.