Section 12-220-15 - Permits
Current through August, 2024
(a) An installation permit shall be issued by the department based on the approval of drawings and specifications pertaining to the installation of pressure retaining items. An application shall be submitted in the prescribed form and must be accompanied by the remittance fee for each pressure retaining item subject to this part as per the schedule in Exhibit A, titled, "Installation, Repair or Alteration Permit Fees, and Licensure, Examination, and Registration Fees", dated September 1, 2019, which is made part of this chapter, and located at the end of this chapter, and inspection fee for each boiler, pressure vessel, or pressure system subject to this part as per the schedule in Exhibit B, titled, "Internal & External Inspection Fees", dated September 1, 2019, which is made a part of this chapter and located at the end of this chapter.
The contractor shall be responsible for furnishing to the department all documentation required and referenced in the standards and codes adopted by the department for installation, construction, routine repair, repair, or alteration of any pressure retaining item, NBEP, and HEP.
(b) No person shall install, construct, reconstruct, or relocate any pressure retaining item without first obtaining an installation permit from the department.
(c) Permits for repairs, routine repairs, or alterations shall be issued upon the approval of code routine repair, repair, or alteration application submitted by the holder of NB "R" certificate of authorization. An application shall be submitted in the prescribed form and must be accompanied by the remittance of the fee for each pressure retaining item subject to this part as per the schedule in Exhibit A, titled, "Installation, Repair or Alteration Permit Fees, and Licensure, Examination, and Registration Fees", dated September 1, 2019, which is made part of this chapter and located at the end of this chapter provided that:
(d) Permits to operate or certificates of inspection shall be issued based on the report of the acceptance inspection and each permit renewal inspection.
(e) The department shall issue a permit to operate for any pressure retaining item required by these rules and inspected by an inspector and found to be safe and in compliance with this subtitle. The owner or user shall remit upon application an inspection fee for each pressure retaining item subject to this part as per the schedule in Exhibit B, titled, "Internal & External Inspection Fees", dated September 1, 2019, which is made a part of this chapter and located at the end of this chapter. It shall be unlawful for any person, firm, association, partnership, or corporation to operate a pressure retaining item regulated by this chapter unless a permit for the operation has been authorized by the department and the permit remains in effect provided that: